Back to projects
Wastewater & DrainageSite SupervisionSetting Out / QA-QC
Tulcan Combined Sewerage & Drainage Upgrade
- Location
- Tulcan, Ecuador
- Period
- 2021-2023
- Role
- Site Engineer / Resident Engineer
- Typology
- Combined sewerage and urban drainage infrastructure
- Status
- Completed
- Upgrade value
- Approx. €492k
- Trunk sewer
- DN 800
- Network
- Approx. 2 km
- Discipline
- Large-diameter drainage
Challenge
Reduce recurring flooding risk, renew existing combined sewerage infrastructure and prepare the area for subsequent urban works.
Technical contribution
- 01Supervised civils, pipe installation, manholes, bedding and backfill coordination.
- 02Verified line, level and gradient during setting out and installation.
- 03Coordinated inspection and test plan hold points.
- 04Managed site diary, daily progress records and as-built information.
- 05Supported BoQ tracking, valuations and handover documentation.
Visual archive
Temporary reference imagery.
These visuals support the portfolio layout until approved real photography is added.

Interim AI visualReplace with approved project photo
Longitudinal profile placeholderReplace with project image